On going Infra Projects

Sl.No. Name of Project Total Cost of Project (In Cr.) Remarks
1 Improving the capacity utilization of OR- 1and OR-2 berths (Construction of OR-I, OR-II & OR-III berths) 167.66

Phase-I: OR-III berth work completed on 10.07.2020 and commissioned on 16.02.2021.

Phase-II: OR-I berth work completed and inaugurated on 04.09.23 & operations commenced on 07.10.2023.

Phase-III: OR-II berth completed, substantially and Dredging work is in progress.

2 Construction of covered storage shed No. 3 of size 200x40x17m at R-10 area in Port. 22.50

Work completed.


3 Rehabilitation of Deck structure of Sardar Vallabhai Patel bridge (Parallel bridge). 25.90

Work is in progress.

Physical Progress: 80.00%
4

Modernization & up gradation of Fishing Harbour at Visakhapatnam Port - Phase-I


37.26

works  in progress.

Physical Progress: 68.85%


5

Modernization & up gradation of Fishing Harbour at Visakhapatnam Port - Phase III


32.86

Work order issued to M/s. Shrushti Contech Pvt. Ltd. on 24.04.2023.

Work is in progress.

Physical Progress: 17.90%

6 Modernization & up gradation of Fishing Harbour at Visakhapatnam Port - ETP’s - Phase IV 5.27

Work order issued to M/s. Aquachem EnviroEngineers Pvt. Ltd., on 24.08.2023.

Physical Progress: 97.00%

07Improvement of Visakhapatnam Railway tracks & rectification of sharp curves more than 10 degrees21.69

Track works completed for a length of 4.00 KM. / 7.7 KM

 Physical Progress: 77.50%

08Up-gradation of East yard railway tracks in VPT17.03

3.00 KM track work completed./5.5 KM and  4 sets of points renewed / 12 points

Physical Progress: 61.19%

09Modernization & up gradation of Fishing Harbour at Visakhapatnam Port – Dredging Work – Phase-VI5.92
Work order issued on 29-01-2024
Dredging work was commenced on 03-05-2024  and  is in progress
Physical Progress : 96.30%
10.Modernization and up gradation of Fishing Harbour at Visakhapatnam Port – Phase-V 32.61Work order issued on 19-02-2025. Finger jetty 1 piling, finger jetty 2 gartry erection & precast concrete works are in progress. Physical Progress 1.50%
11.Construction of customs boundary wall at VPA7.17

Work is in progress.

Physical Progress: 97.00%
12.Construction of two additional breasting dolphins (BD-3 and BD-4) to accommodate medium range vessels at OSTT of Visakhapatnam Port.20.87

Work order issued  on 17-10-2024.

Work was commenced on 16-11-2024 & Soil investigation was completed and mobilization is in progress for test piles.

Physical Progress

13Repairs to the pockets along the SL canal Jetty and Backup area to avoid erosion of bund (berthing area for Port crafts) 15.02

Liners driven –completed- 136/ 290 Nos, Piles – Completed – 100/ 290 Nos.

Physical Progress: 3.80%

14Development of Public Promenade near Cruise Terminal in Visakhapatnam Port Authority.15.90

Work order issued on 07-02-2025 and Work commenced on 21-02-2025.

Compound wall Plastering, Parking area, toilet building works, Parking Area retaining wall and Anchorage works are in progress.

Physical Progress: 15.00%

15.Feasibility study for establishing a major port cum ship building cum repair cluster in AP.16.90

M/s RITES furnished TEFR as per the directions of JS (ports), TEFR being vetting by KOMAC.

Physical Progress: 90.00%
16.Up-gradation of existing MCHV Railway track up to silo and laying of locomotive reversal line.6.60

Sub grade preparation for laying of track is under progress.

Physical Progress: 7.00%
17.Procurement of P.way materials for Maintenance of Railway lines for 03 years (2024-27).15.79

Ballast collection is in progress at site of work and Crossing bodies & switches received at site of work.

Physical Progress: 14.00%
18.Supply & Installation of continuous ambient air quality, marine water quality, effluent monitoring system at STP, online sound level with10 years CAMC in port area.7.43

Pre Bids opened on 10.07.2025.


T.C meeting held on 14.07.2025and  committee minutes under finalization

19.Providing RCC drain in place of existing kutcha drain from Dr.B.R.Ambedkar fly over bridge west end to joining at Megadri gedda.9.49

Work order issued to L1 bidder  on 14.07.2025

20.Providing Office facilities for Customs, CISF & VPA staff at newly Constructed RFID gates in Port area.7.29

NIT issued on 21.05.2025

T.B’s opened on 26.06.2025 and evaluation going on.

PROPOSAL STAGE WORKS

 

S.No.

Name of the project

Remarks

1.

Development of internal flyovers in Port area.

Consultancy Work awarded to M/s RVNL to review the DPR submitted by M/s IPRCL. M/s. RVNL furnished draft DPR

2.

Conversion of existing Rail bridge to Road bridge and to provide a two lane BG track Rail bridge over Meghadri gedda.

Consultancy Work will be awarded to M/s RVNL to prepare DPR

3.

Deepening of the Entrance Channel & Inner Harbour and Strengthening of existing berths in Visakhapatnam Port.

Consultancy work awarded to NTCPWC to prepare  Detailed Project Report (DPR)

4.

Rehabilitation of Jetty No’s- 1, 2, 3, 4, Wet Basin & DC Jetty in the Entrance Channel of Visakhapatnam Port.

Work order issued on 11.03.2024 to IIT-madras to prepare TEFR. TEFR is under finalization.

5.

Strengthening of WQ-1, WQ-2, WQ-3 berths for an additional dredge depth from  (-)14.00m to  (-)15.50m

Consultancy work awarded to IIT Madras

6.

Construction of B-Ramp to facilitate movement of cargo from Eastern & Western Quays

Letter has been addressed on 02.04.2025 to  NHAI authorities regarding the VPA's board approval for the proposal of reconstruction of B-ramp.

7

Construction of new multistoried building in port area to accommodate all departments.

Work awarded to NBCC on deposit basis.

8.

Construction of additional ramp to facilitate movement of trucks from Ambedkar Centenary Flyover to L-15/17 corridor

Work awarded to NHAI on deposit basis 


last update on 28-07-2025