On going Infra Projects
| Sl.No. | Name of Project | Total Cost of Project (In Cr.) | Remarks |
| 1 | Improving the capacity unilization of OR-I and OR-II berths (Construction of OR-I OR-II & OR-III | 167.66 |
Phase-I: OR-III berth work
completed on 10.07.2020 and commissioned on 16.02.2021. Phase-II: OR-I berth work completed
and inaugurated on 04.09.23 & operations commenced on 07.10.2023. Phase-III: OR-II berth completed, - Demolition of old OR-II monoliths by underwater controlled blasting in window at OR-I for 3 monoliths and in non-window for balance monoliths. - Dredging in soft soil, stiff clay & channel is in progress with approved window for vessel movements in the channel.
|
| 2 | Construction of covered storage shed No. 3 of size 200x40x17m at R-10 area in Port. | 22.50 |
Work completed. |
| 3 | Rehabilitation of Deck structure of Sardar Vallabhai Patel bridge (Parallel bridge). | 25.90 |
Work completed |
| 4 | Modernization & up gradation of Fishing Harbour at
Visakhapatnam Port - Phase-I |
37.26 |
- Chill room MEWP, Parking area Brick masonry, plastering, granite fixing, painting works are in progressworks in progress. - Physical Progress: 79.40% - Road & drainage works under progress. |
| 5 | Modernization & up gradation of Fishing Harbour at
Visakhapatnam Port - Phase III |
32.86 |
- Work order issued to M/s. Shrushti Contech Pvt. Ltd. on 24.04.2023. - Auction hall-3 completed - Aucation hall-1 work is yet to be commenced since the present users to be shifted to auction hall-2 after its completion. - Aucation hall-2 structural fabrication erection & painting works are in progress. - Physical Progress: 30.00% |
| 6 | Modernization & up gradation of Fishing Harbour at Visakhapatnam Port - ETP’s - Phase IV | 5.27 |
Work completed |
| 07 | Improvement of Visakhapatnam Railway tracks & rectification of sharp curves more than 10 degrees | 21.69 | - Track works completed for a length of 4.00 KM. / 7.7 KM - Track work at 8 locations completedpreparatory work are under progress for 9th location. - placing of rails on the sleepers work is in progress. - Physical Progress: 87.00% |
| 08 | Up-gradation of East yard railway tracks in VPT | 17.03 | - Rank vegetation between railway track, laying of sleepers and packing of ballast is in progress - L-15 Line Laying and packing of ballast and placing of sleepers is in progress. - Physical Progress: 65.50% |
| 09 | Modernization & up gradation of Fishing Harbour at Visakhapatnam Port – Dredging Work – Phase-VI | 5.92 | Work completed |
| 10. | Modernization and up gradation of Fishing Harbour at Visakhapatnam Port – Phase-V | 32.61 | - Work order issued on 19-02-2025. - Finger jetty 1 & 2 precast erection & Wharf piling, precast concrete works are in progress. - Physical Progress: 16.45% |
| 11. | Construction of customs boundary wall at VPA | 7.17 | - Raft reinforement tying, concreting and wall plastering works are in progress. - Physical Progress: 97.50% |
| 12. | Construction of two additional breasting dolphins (BD-3 and BD-4) to accommodate medium range vessels at OSTT of Visakhapatnam Port. | 20.87 | - Work order issued on 17-10-2024.
- Work was commenced on 16-11-2024 & Soil investigation was completed, Pile concrete for Pull out test completed and boring work for support pile of pull test pile is in progress. - Physical Progress: 5.75% |
| 13 | Repairs to the pockets along the SL canal Jetty and Backup area to avoid erosion of bund (berthing area for Port crafts) | 15.02 | - Liners driven –completed- 260/ 290 Nos, Piles – Completed – 227/ 290 Nos. - Earth work of Rock bund along the steet piling & rock bund filling is completed 225m against 314m. - Physical Progress: 95.80% |
| 14 | Development of Public Promenade near Cruise Terminal in Visakhapatnam Port Authority. | 15.90 | - Work
order issued on 07-02-2025 and Work commenced on 21-02-2025. - Plantation at landscaping, other finishing works such as cleaning, tiles for SS rail beam works etc., are in progress - Physical Progress: 90.00% |
| 15. | Feasibility study for establishing a major port cum ship building cum repair cluster in AP. | 17.92 | - Work completed. |
| 16. | Up-gradation of existing MCHV Railway track up to silo and laying of locomotive reversal line. | 6.60 | - Noth cabin side point on 225 renewasl work is in progress. |
| 17. | Procurement of P.way materials for Maintenance of Railway lines for 03 years (2024-27). | 15.79 | - Shifting and renewal of sleepers is in progress at site of work and switches received at site of the work. |
| 18. | Supply & Installation of continuous ambient air quality, marine water quality, effluent monitoring system at STP, online sound level with10 years CAMC in port area. | 7.43 | - Work order issued on 19-08-2025.
|
| 19. | Providing RCC drain in place of existing kutcha drain from Dr.B.R.Ambedkar fly over bridge west end to joining at Megadri gedda. | 9.49 | - Work commenced on 28-07-2025. - Reinforcement tying for Drain wall from ch 191.00m to h 210.00m work is in progress. - Physical Progress: 36.00% |
| 20. | Providing Office facilities for Customs, CISF & VPA staff at newly Constructed RFID gates in Port area. | 7.29 | - 2nd Slab casting completed for CISF and Custom buildings. 2nd floor slab shutteering completed & reinforcement tying is in progressand G/F Brickwork completed for CISF Building @ H7 RFID gate. - Physical Progress: 23.00% |
|
PROPOSAL STAGE WORKS
|
||
|
S.No. |
Name of the project |
Remarks |
|
1. |
Development
of internal flyovers in Port area. |
- Consultancy
work awarded to M/s RVNL to review the DPR submitted by M/s IPRCL. - Board note put up on 06.02.2026 for approval of Board to the estimated cost of Rs.334.89Cr. |
|
2. |
Conversion of existing Rail bridge
to Road bridge and to provide a two lane BG track Rail bridge over Meghadri
gedda. |
- VPA
& RVNL entered into an agreement for the study of the subject work. - Work order issued to M/s RVNL vide, W.O.No. 04 of EE(P&D)2025-26, dt.25.08.2025 |
|
3. |
Deepening of the Entrance Channel
& Inner Harbour and Strengthening of existing berths in Visakhapatnam
Port. |
- Consultancy
awarded to NTCPWC to prepare Detailed Project Report (DPR) - Letter is addressed to NTCPWC on 20.11.2025 to furnish the DPR for Phase-I dredging. |
|
4. |
Rehabilitation of Jetty No’s- 1,
2, 3, 4, Wet Basin & DC Jetty in the Entrance Channel of Visakhapatnam
Port. |
- Work order issued on 11.03.2024 to IIT-madras to prepare TEFR. |
|
5. |
Strengthening of WQ-1, WQ-2, WQ-3
berths for an additional dredge depth from
(-)14.00m to (-)15.50m |
- Consultancy
awarded to IIT Madras on 09.10.2025 to conduct NDT tests. - IIT Madras furnished NDT Report on 24.11.2025 the same was forwarded to EE(South) on 25.11.2025 for further necessary action. |
|
6. |
Construction of B-Ramp to
facilitate movement of cargo from Eastern & Western Quays |
- Letter
has been addressed on 02.04.2025 to NHAI authorities regarding the VPA board’s
approval for the proposal of re-construction of B-ramp. - Geo-Technical investigation is under progress. |
|
7 |
Construction of new multistoried
building in port area to accommodate all departments. |
- Work
awarded to NBCC on deposit basis. - NBCC
furnished estimate at a cost of Rs.97.74Cr. - Dismantling
of Old DCI building is in progress which is taken up by VPA. - Upon
dismantling of the Old DCI building, NBCC will call tenders. - Expected date for calling tenders is 25.01.2026. |
|
8. |
Construction of additional ramp to
facilitate movement of trucks from Ambedkar Centenary Flyover to L-15/17
corridor |
- Work awarded to NHAI on deposit basis after taking approval from the Competent Authority. |
| 9. | Construction of Residential apartments for Visakhapatnam Port Authority at Harbour Park. | - Work
awarded to CPWD. - CPWD
submitted cost estimate for an amount of Rs.49.90Cr. - CPWD
is under the process of calling tenders. |