1 |
Improving the capacity utilization of OR-
1and OR-2 berths (Construction of OR-I,
OR-II & OR-III berths) |
167.66
|
-
Phase-I: OR-III berth work completed on 10.07.2020 and
commissioned on 16.02.2021.
-
Phase-II: OR-I berth work completed and inaugurated on
04.09.23 & operations commenced on 07.10.2023.
-
Phase-III:
Deck slab and foundation, dredging work is in progress
-
Physical Progress: 78.04%
|
2 |
Construction of covered storage shed No.
3 of size 200x40x17m at R-10 area in Port. |
22.50
|
-
Work is in progress.
-
Physical Progress: 55.68%
|
3 |
Rehabilitation of Deck structure of Sardar
Vallabhai Patel bridge (Parallel bridge). |
25.90
|
-
Work is in progress.
-
Bridge handed over to the Contractor from 01.04.2024 ,but
due to technical issue the road bridge opened again as per
the instructions of ADCP.
-
Physical Progress: 49.00%
|
4 |
Modernization & up gradation of Fishing
Harbour at Visakha-patnam Port - Phase-I |
37.26
|
-
Net Mending Building painting works, Packing unit & cold
chamber Brick masonry works and plastering works,
Parking area slab works, Road & drainage works and Gate
complex works under progress.
-
Physical Progress: 57.00%
|
5 |
Modernization & upgradation of Fishing
Harbour at Visakha-patnam Port - Phase
III |
32.86
|
-
Work order issued to M/s. Shrushti Contech Pvt. Ltd. on
24.04.2023.
-
Existing Lessee has been vacated and the foundation
works for Auction Hall-02 commenced on 19.12.23 and is in
progress.
-
Physical Progress: 9.75%
|
6 |
Modernization & upgradation of Fishing
Harbour at Visakhapatnam Port - ETP’s -
Phase IV |
5.27
|
-
Work order issued to M/s. Aquachem Enviro Engineers Pvt.
Ltd., on 24.08.2023 for an amount of Rs.5.27 Cr.
-
Work was commenced on 07.09.2023 & is in progress
-
Physical Progress: 66.00%
|
7 |
Improvement of Visakhapatnam Railway
tracks & rectification of sharp curves more
than 10 degrees |
21.69
|
-
IPRCL has been procuring the 60 Kg Rails, sleepers etc.
-
Physical Progress: 50.30%
|
8 |
Up-gradation of East yard railway tracks in
VPA |
17.03
|
-
Procurement of material is in progress.
-
Physical Progress: 49.80%
|
9 |
Modernization & upgradation of Fishing
Harbour at Visakhapatnam Port –
Dredging Work – Phase-VI |
5.92
|
-
Work order issued on 29.01.2024.
-
The work has been commenced on 16.02.2024 and
mobilization is in progress.
|
10 |
Modernization and up gradation of Fishing
Harbour at Visakhapatnam Port - Supply,
Installation, Commissioning and Testing of
Floating Jetty – Phase-V |
9.49
|
-
The Bid opened on 04.05.2023 (3rd call) and no one
participated.
-
Fishermen requested for permanent jetty instead of
Floating Jetty.
-
A letter has been addressed to the Secretary, MoPSW &
Ministry of Fisheries on 26.09.2023 for revised scope of
work.
|
11 |
Construction of two additional breasting
dolphins (BD-3 and BD-4) to accommodate
medium range vessels at OSTT of
Visakhapatnam Port. |
18.63
|
-
NIT issued on 05.02.2024.
-
Bids opened on 07.03.2024 & evaluation completed.
-
Note processed to accord sanction to open the price bid.
|
12 |
Repairs to the pockets along the SL canal
Jetty and Backup area to avoid erosion of
bund (berthing area for Port crafts) |
14.48
|
-
NIT issued on 26.04.2024.
-
Bid opening Date 29.05.2024
|
13 |
Providing New Fire Fighting Facilities suitable to the
upgrading capacities of Berths OR-l & ll to accommodate
50,000 to 1,00,000 DWT Vessels (Panamax Vessels) as
per OISD 156 guidelines in a phased manner- Phase-I |
4.22
|
The existing Fire Fighting Facilities
are suitable for handling vessels of
Capacity up to 50,000 DWT. Hence
the Fire Fighting Facilities are
enhancing to accommodate the
Vessels of capacity 50,000 to
1,00,000 DWT.
|
14 |
Providing New Fire Fighting Facilities suitable to the
upgrading capacities of Berths OR-l & ll to accommodate
50,000 to 1,00,000 DWT Vessels (Panamax Vessels) as
per OISD 156 guidelines in a phased manner- Phase-II |
27.13
|
The existing Fire Fighting Facilities
are suitable for handling vessels of
Capacity up to 50,000 DWT. Hence
the Fire Fighting Facilities are
enhancing to accommodate the
Vessels of capacity 50,000 to
1,00,000 DWT.
|
15 |
Up-gradation of Fire Fighting Facilities for OSTT Berth to
accommodate Vessels of capacity 1,00,000 DWT and
above (Cape size Vessels) as per OISD 156 guidelines
including Annual Maintenance Contract (AMC) for 10 (ten)
years for Operations and Maintenance ( O & M ) of
Upgraded Fire Fighting Facilities of OSTT”. |
28.59
|
The existing Fire Fighting Facilities
are suitable for handling vessels of
Capacity up to 50,000 DWT. Hence
the Fire Fighting Facilities are
enhancing to accommodate the
Vessels of capacity above 1,00,000
DWT.
|
16 |
Mechanization of WQ-7 & 8 Berths at Visakhapatnam Port |
288.47
|
VPT Envisaged to develop WQ-7 &
WQ-8 Berths by provding
mechanized handling facilities to
handle bulk cargoes. These berths
were constructed with internal
resources at a cost of Rs, 243/-
Crores. Total legth of the Berth is
560 mtrs. Capacity 6.14 MTPA.
|
17 |
Mechanization of EQ-7 Berth at Visakhapatnam Port. |
200.99
|
VPT Envisaged to develop EQ-7
Berth by provding mechanized
handling facilities to handle multiple
cargoes including fertilizers. Total
legth of the Berth is 255 mtrs.
Capacity 3.61 MTPA.
|
18 |
Smart Port Surveillance using AI & VA for Port shipping
Railway operation. |
25 Cr.
|
In order to improve operational
efficiency in VPA like ship arrivals,
ship departures, Idle Hours, Berth
occupancy, Berth utilitiesation,
similarly detection & Pointing alerts
while congestion at gates, Tarpoulin
Coverage of coal stacks, unmanned
Railway crossing etc.
|
19 |
Extension of Port Custom bound area by providing new
gates Infrastructure. |
1.40Lacs
|
Improving Vehicle movement, better
connectivity to storage area, reduce
vehicle congestion, smooth road
traffic to evacuate Cargo faster.
|
20 |
PMC work for development of 33/11 KV outdoor Substation
at VPA. |
0.37Cr.
|
Work order awarded to M/s PTC
India Ltd., New Delhi
|
21 |
Electrification of 38 TKM Railways lines in 3 phases. |
21.09
|
Work order awarded to M/s IPRCL,
Visakhapatnam.
|
22 |
Operational & Maintenance of EQ1 terminal. |
42.44
|
Work order awarded to M/s HIQ
services and feedback power
operation and maintenance services
private ltd.
|