On going Infra Projects
Sl.No. | Name of Project | Total Cost of Project (In Cr.) | Remarks |
1 | Improving the capacity utilization of OR- 1and OR-2 berths (Construction of OR-I, OR-II & OR-III berths) | 167.66 |
Phase-I: OR-III berth work
completed on 10.07.2020 and commissioned on 16.02.2021. Phase-II: OR-I berth work completed
and inaugurated on 04.09.23 & operations commenced on 07.10.2023. Phase-III: OR-II berth completed, substantially and Dredging work is in progress. |
2 | Construction of covered storage shed No. 3 of size 200x40x17m at R-10 area in Port. | 22.50 |
Work completed. |
3 | Rehabilitation of Deck structure of Sardar Vallabhai Patel bridge (Parallel bridge). | 25.90 |
Work
is in progress. |
4 | Modernization & up gradation of Fishing Harbour at
Visakhapatnam Port - Phase-I |
37.26 |
works in progress. Physical Progress: 68.85% |
5 | Modernization & up gradation of Fishing Harbour at
Visakhapatnam Port - Phase III |
32.86 |
Work order issued to M/s. Shrushti Contech Pvt. Ltd. on 24.04.2023. Work is
in progress. Physical Progress: 17.90% |
6 | Modernization & up gradation of Fishing Harbour at Visakhapatnam Port - ETP’s - Phase IV | 5.27 |
Work order issued to M/s. Aquachem EnviroEngineers Pvt. Ltd., on 24.08.2023. Physical Progress: 97.00% |
07 | Improvement of Visakhapatnam Railway tracks & rectification of sharp curves more than 10 degrees | 21.69 | Track
works completed for a length of 4.00 KM. / 7.7 KM Physical Progress: 77.50% |
08 | Up-gradation of East yard railway tracks in VPT | 17.03 | 3.00 KM track work completed./5.5 KM and 4 sets of points renewed / 12 points Physical Progress: 61.19% |
09 | Modernization & up gradation of Fishing Harbour at Visakhapatnam Port – Dredging Work – Phase-VI | 5.92 | Work order issued on 29-01-2024 Dredging work was commenced on 03-05-2024 and is in progress Physical Progress : 96.30% |
10. | Modernization and up gradation of Fishing Harbour at Visakhapatnam Port – Phase-V | 32.61 | Work order issued on 19-02-2025. Finger jetty 1 piling, finger jetty 2 gartry erection & precast concrete works are in progress. Physical Progress 1.50% |
11. | Construction of customs boundary wall at VPA | 7.17 | Work is in progress. |
12. | Construction of two additional breasting dolphins (BD-3 and BD-4) to accommodate medium range vessels at OSTT of Visakhapatnam Port. | 20.87 | Work order issued on 17-10-2024.
Work was commenced on 16-11-2024 & Soil investigation was completed and mobilization is in progress for test piles. Physical Progress |
13 | Repairs to the pockets along the SL canal Jetty and Backup area to avoid erosion of bund (berthing area for Port crafts) | 15.02 | Liners driven –completed-
136/ 290 Nos, Piles – Completed – 100/ 290 Nos. Physical Progress: 3.80% |
14 | Development of Public Promenade near Cruise Terminal in Visakhapatnam Port Authority. | 15.90 | Work
order issued on 07-02-2025 and Work commenced on 21-02-2025. Compound wall Plastering, Parking area, toilet building works, Parking Area retaining wall and Anchorage works are in progress. Physical Progress: 15.00% |
15. | Feasibility study for establishing a major port cum ship building cum repair cluster in AP. | 16.90 | M/s
RITES furnished TEFR as per the directions of JS (ports), TEFR being vetting by
KOMAC. |
16. | Up-gradation of existing MCHV Railway track up to silo and laying of locomotive reversal line. | 6.60 | Sub
grade preparation for laying of track is under progress. |
17. | Procurement of P.way materials for Maintenance of Railway lines for 03 years (2024-27). | 15.79 | Ballast
collection is in progress at site of work and Crossing bodies & switches
received at site of work. |
18. | Supply & Installation of continuous ambient air quality, marine water quality, effluent monitoring system at STP, online sound level with10 years CAMC in port area. | 7.43 | Pre Bids opened on 10.07.2025. T.C meeting held on 14.07.2025and committee minutes under finalization |
19. | Providing RCC drain in place of existing kutcha drain from Dr.B.R.Ambedkar fly over bridge west end to joining at Megadri gedda. | 9.49 | Work order issued to L1
bidder on 14.07.2025 |
20. | Providing Office facilities for Customs, CISF & VPA staff at newly Constructed RFID gates in Port area. | 7.29 | NIT issued on 21.05.2025 |
PROPOSAL STAGE WORKS
|
||
S.No. |
Name of the project |
Remarks |
1. |
Development
of internal flyovers in Port area. |
Consultancy Work awarded to M/s RVNL to review the
DPR submitted by M/s IPRCL. M/s. RVNL furnished draft DPR |
2. |
Conversion of existing Rail bridge
to Road bridge and to provide a two lane BG track Rail bridge over Meghadri
gedda. |
Consultancy Work will be awarded to M/s RVNL to
prepare DPR |
3. |
Deepening of the Entrance Channel
& Inner Harbour and Strengthening of existing berths in Visakhapatnam
Port. |
Consultancy
work awarded to NTCPWC to prepare
Detailed Project Report (DPR) |
4. |
Rehabilitation of Jetty No’s- 1,
2, 3, 4, Wet Basin & DC Jetty in the Entrance Channel of Visakhapatnam
Port. |
Work order issued on 11.03.2024 to IIT-madras to prepare TEFR. TEFR is
under finalization. |
5. |
Strengthening of WQ-1, WQ-2, WQ-3
berths for an additional dredge depth from
(-)14.00m to (-)15.50m |
Consultancy work
awarded to IIT Madras |
6. |
Construction of B-Ramp to
facilitate movement of cargo from Eastern & Western Quays |
Letter has been addressed on 02.04.2025 to NHAI authorities regarding the VPA's board approval for the proposal of reconstruction of B-ramp. |
7 |
Construction of new multistoried
building in port area to accommodate all departments. |
Work awarded to NBCC on
deposit basis. |
8. |
Construction of additional ramp to
facilitate movement of trucks from Ambedkar Centenary Flyover to L-15/17
corridor |
Work awarded to
NHAI on deposit basis |