On going Infra Projects

Sl.No. Name of Project Total Cost of Project (In Cr.) Remarks
1 Improving the capacity unilization of OR-I and OR-II berths (Construction of OR-I OR-II & OR-III 167.66

Phase-I: OR-III berth work completed on 10.07.2020 and commissioned on 16.02.2021.

Phase-II: OR-I berth work completed and inaugurated on 04.09.23 & operations commenced on 07.10.2023.

Phase-III: OR-II berth completed, 

- Demolition of old OR-II monoliths by underwater controlled blasting in window at OR-I for 3 monoliths and in non-window for balance monoliths.

- Dredging in soft soil, stiff clay & channel is in progress with approved window for vessel movements in the channel.

                    

2 Construction of covered storage shed No. 3 of size 200x40x17m at R-10 area in Port. 22.50

Work completed.


3 Rehabilitation of Deck structure of Sardar Vallabhai Patel bridge (Parallel bridge). 25.90

Work completed

4

Modernization & up gradation of Fishing Harbour at Visakhapatnam Port - Phase-I


37.26

- Chill room MEWP, Parking area Brick masonry, plastering, granite fixing, painting works are in progressworks  in progress.

- Physical Progress: 79.40%

- Road & drainage works under progress.


5

Modernization & up gradation of Fishing Harbour at Visakhapatnam Port - Phase III


32.86

- Work order issued to M/s. Shrushti Contech Pvt. Ltd. on 24.04.2023.

- Auction hall-3 completed

- Aucation hall-1 work is yet to be commenced since the present users to be shifted to auction hall-2 after its completion.

- Aucation hall-2 structural fabrication erection & painting works are in progress.

- Physical Progress: 30.00%

6 Modernization & up gradation of Fishing Harbour at Visakhapatnam Port - ETP’s - Phase IV 5.27

Work  completed

07Improvement of Visakhapatnam Railway tracks & rectification of sharp curves more than 10 degrees21.69

- Track works completed for a length of 4.00 KM. / 7.7 KM

- Track work at 8 locations completedpreparatory work are under progress for 9th location.

- placing of rails on the sleepers work is in progress.

- Physical Progress: 87.00%

08Up-gradation of East yard railway tracks in VPT17.03

- Rank vegetation between railway track, laying of sleepers and packing of ballast is in progress

- L-15 Line Laying and packing of ballast  and placing of sleepers is in progress.

- Physical Progress: 65.50%

09Modernization & up gradation of Fishing Harbour at Visakhapatnam Port – Dredging Work – Phase-VI5.92
Work completed
10.Modernization and up gradation of Fishing Harbour at Visakhapatnam Port – Phase-V 32.61

- Work order issued on 19-02-2025.

- Finger jetty 1 & 2 precast erection & Wharf piling, precast concrete works are in progress.

- Physical Progress: 16.45%

11.Construction of customs boundary wall at VPA7.17

- Raft reinforement tying, concreting and wall plastering works are in progress.

- Physical Progress: 97.50%

12.Construction of two additional breasting dolphins (BD-3 and BD-4) to accommodate medium range vessels at OSTT of Visakhapatnam Port.20.87

- Work order issued  on 17-10-2024.

- Work was commenced on 16-11-2024 & Soil investigation was completed, Pile concrete for Pull out test completed and boring work for support pile of pull test pile is in progress.

- Physical Progress: 5.75%

13Repairs to the pockets along the SL canal Jetty and Backup area to avoid erosion of bund (berthing area for Port crafts) 15.02

- Liners driven –completed- 260/ 290 Nos, Piles – Completed – 227/ 290 Nos.

- Earth work of Rock bund along the steet piling & rock bund filling is completed 225m against 314m.

- Physical Progress: 95.80%

14Development of Public Promenade near Cruise Terminal in Visakhapatnam Port Authority.15.90

- Work order issued on 07-02-2025 and Work commenced on 21-02-2025.

- Plantation at landscaping, other finishing works such as cleaning, tiles for SS rail beam works etc., are in progress

- Physical Progress: 90.00%

15.Feasibility study for establishing a major port cum ship building cum repair cluster in AP.17.92

- Work completed.


16.Up-gradation of existing MCHV Railway track up to silo and laying of locomotive reversal line.6.60

- Noth cabin side point on 225 renewasl work is in progress.

- Physical Progress: 85.00%
17.Procurement of P.way materials for Maintenance of Railway lines for 03 years (2024-27).15.79

- Shifting and renewal of sleepers is in progress at site of work and switches received at site of the work.

- Physical Progress: 27.10%
18.Supply & Installation of continuous ambient air quality, marine water quality, effluent monitoring system at STP, online sound level with10 years CAMC in port area.7.43

- Work order issued on 19-08-2025.


- The PA officials from Environment cell, M&EE department and IT section to visit KOTA for inspection of the CAAQM statioins equipment.

19.Providing RCC drain in place of existing kutcha drain from Dr.B.R.Ambedkar fly over bridge west end to joining at Megadri gedda.9.49

- Work commenced on 28-07-2025.

- Reinforcement tying for Drain wall from ch 191.00m to h 210.00m work is in progress.

- Physical Progress: 36.00%

20.Providing Office facilities for Customs, CISF & VPA staff at newly Constructed RFID gates in Port area.7.29

- 2nd Slab casting completed for CISF and Custom buildings. 2nd floor slab shutteering completed & reinforcement tying is in progressand G/F Brickwork completed for CISF Building @ H7 RFID gate.

- Physical Progress: 23.00%

PROPOSAL STAGE WORKS

 

S.No.

Name of the project

Remarks

1.

Development of internal flyovers in Port area.

- Consultancy work awarded to M/s RVNL to review the DPR submitted by M/s IPRCL.

- Board note put up on 06.02.2026 for approval of Board to the estimated cost of Rs.334.89Cr.

2.

Conversion of existing Rail bridge to Road bridge and to provide a two lane BG track Rail bridge over Meghadri gedda.

- VPA & RVNL entered into an agreement for the study of the subject work.

- Work order issued to M/s RVNL vide, W.O.No. 04 of EE(P&D)2025-26, dt.25.08.2025

3.

Deepening of the Entrance Channel & Inner Harbour and Strengthening of existing berths in Visakhapatnam Port.

- Consultancy awarded to NTCPWC to prepare Detailed Project Report (DPR)

- Letter is addressed to NTCPWC on 20.11.2025 to furnish the DPR for Phase-I dredging.

4.

Rehabilitation of Jetty No’s- 1, 2, 3, 4, Wet Basin & DC Jetty in the Entrance Channel of Visakhapatnam Port.

- Work order issued on 11.03.2024 to IIT-madras to prepare TEFR.

5.

Strengthening of WQ-1, WQ-2, WQ-3 berths for an additional dredge depth from  (-)14.00m to  (-)15.50m

- Consultancy awarded to IIT Madras on 09.10.2025 to conduct NDT tests.

- IIT Madras furnished NDT Report on 24.11.2025 the same was forwarded to EE(South) on 25.11.2025 for further necessary action.

6.

Construction of B-Ramp to facilitate movement of cargo from Eastern & Western Quays

- Letter has been addressed on 02.04.2025 to NHAI authorities regarding the VPA board’s approval for the proposal of re-construction of B-ramp.

- Geo-Technical investigation is under progress.

7

Construction of new multistoried building in port area to accommodate all departments.

- Work awarded to NBCC on deposit basis.

- NBCC furnished estimate at a cost of Rs.97.74Cr.

- Dismantling of Old DCI building is in progress which is taken up by VPA.

- Upon dismantling of the Old DCI building, NBCC will call tenders.

- Expected date for calling tenders is 25.01.2026.

8.

Construction of additional ramp to facilitate movement of trucks from Ambedkar Centenary Flyover to L-15/17 corridor

- Work awarded to NHAI on deposit basis after taking approval from the Competent Authority.

9.Construction of Residential apartments for Visakhapatnam Port Authority at Harbour Park.

- Work awarded to CPWD.

- CPWD submitted cost estimate for an amount of Rs.49.90Cr.

- CPWD is under the process of calling tenders.

- Expected date for calling tenders is 25.01.2026